"Vice President of the Supreme Administrative Court" advises Construction permit withdrawal case “Ashton Asoke Condo” has 3 months left to find a solution. If there is no progress, the BMA may have to order the demolition of the part of the building that is taller than the road width to be completed within 90 days.
Today (March 6, 2024) Mr. Prawit Bunthiam, Chairman of the Tort Litigation and Other Liability Division at the highest administrative level. Help work temporarily in the position of Vice President of the Supreme Administrative Court. Addressing the issue of enforcement "Ashton Asoke Case" in which the Supreme Administrative Court ruled to revoke the construction permit said that in this case the court ordered the revocation of the construction permit for the Ashton Asoke building. because it was seen that It is an unlawful issuance of a license.
Therefore, legal enforcement is a matter for Bangkok Metropolitan Administration (Bangkok) to proceed in accordance with the Building Control Act. The court did not order that it must be demolished or that it would enforce the case in any other way.
“So about 3 months from now. It will be due according to the judgment that ordered the BMA, Ananda FM Asia Asoke Company Limited and the Mass Rapid Transit Authority of Thailand (MRTA) to expedite the resolution of the problem in accordance with the Building Control Act. within 180 days